Assessment for lifting general projects shall comply with the provisions

Published on by YT electric hoists

Assessment for lifting general projects shall comply with the provisions

1, lifting
1) When more than one double beam grab crane while lifting a member, the single crane to withstand loads shall comply with the special construction program requirements;
2) sling hanging points should comply with the special construction program requirements;
3) crane operation, no one should remain below the boom, it should not be hanging objects by people from directly above;
4) gantry crane 40 ton spreader carrying personnel should not be used;
5) When lifting objects scattered easily, you should use special cage.
2, high operating
1) should be required to set the high operating platform;
2) platform strength, fence height shall comply with regulatory requirements;
Intensity 3) ladders, construction should comply with regulatory requirements;
4) There shall be a reliable point seat belt hanging and hanging low to be used.
3, stacking member
1) member shall be stacked load bearing capacity of the work surface within the allowable range;
2) member stacked height should be within the specified range;
3) Large members should ensure the stability of stacking measures.
4, alert monitoring
1) should be required to set up a job alert zone;
2) the warning area should set up special monitoring.

Published on gantry crane 40 ton

To be informed of the latest articles, subscribe:
Comment on this post
G
Thanks for nice information about goliath cranes. Your blog focuses on every detailed aspects which boosted my knowledge regarding cranes. Santek Equipments exports high quality goliath cranes & supply them to various sectors.
Reply
V
Thanks for sharing the grateful information. I regularly visit your website to get information.<br /> V. M. Engineers,Manufacturer & Exporter of Cranes, industrial cranes exporters India, goliath cranes India,EOT crane manufacturers in India
Reply